PAVING UPDATE 6.11.24

Crestline Paving Project

Crestline Paving Project

Crews are continuing to work in the Crestline area to improve the roadway.  

Over the course of this week, they will begin repaving the milled roadways. The paving is expected to occur in the following order: Montrose Road, Old Leeds Road, Beechwood Road, Overbrook Road (toward Cherokee Road), Overbrook Road (toward Montevallo Road). As with all construction projects, these details are subject to change due to weather or other unforeseen circumstances. Public Works hopes to have the project completed by the end of next week.

Please expect detours and delays along the highlighted route as prolonged lane closures are expected. Thank you for your continued patience!