UPDATE: Major Mountain Brook Intersection Temporarily Closing Due to Jefferson County Sanitary Project

September 15, 2023

Phase 3 will start on Monday, September 18, 2023. The Montevallo Road intersection and part of Culver Road up to Rele Street will be closed. (See map for details.) The estimated time of closure is 5-6 weeks, barring unforeseen circumstances. There will be a few days when parts of phase two (Petticoat Lane) and phase three are closed to allow for material and equipment to be relocated and Petticoat Lane is patched with asphalt.

Detours and traffic control signage will be in place. Parking will be affected; however, sidewalks will remain open. We expect this closure to have a major impact on local and commuter traffic. As with the entirety of the project, sidewalks and businesses will remain open. Please seek an alternate route and expect major traffic delays!